November 5, 2026
Since August 25, the stretch of N. Riverside Drive between Coral Way and Sand Dollar Road in unincorporated Indialantic has been closed to through traffic. Drivers heading south have been sent from Eau Gallie Boulevard to A1A to Paradise Boulevard, and drivers heading north take the same loop in reverse. When the full closure ends, the county's plan calls for the road to reopen to a single lane controlled by flaggers for about six months.
That six months is only part of a bigger plan. The county calls this job the second phase of a multi-year drainage project. A state funding request filed for the work lists nine phases, with an estimated total of about $22 million. For anyone who lives off this part of the river, construction on Riverside Drive is going to be part of the routine for a long time.
The City of Melbourne's traffic advisory, published August 17, lists the through-traffic closure from August 25 until November 20. Its closure zone runs from Coral Way to 300 feet south of Sand Dollar Road. Brevard County's August 10 release estimates the full closure at about three months and expects the single-lane phase to begin in early December. The county project page lists one-way traffic for November 2026. Its FAQ says the full closure lasts through early December. The city's notice adds that weather and other unforeseen conditions can shift construction schedules.
Here is the schedule, combining the city's advisory with the county's project page:
| Milestone | Posted timing | What it means on the road |
|---|---|---|
| Full closure begins | August 25, 2026 | Through traffic detoured via Eau Gallie Blvd., A1A and Paradise Blvd. |
| Single-lane phase begins | November 20 to early December 2026 | One lane open, controlled by flaggers |
| Road reopens | Early June 2027 | Contractor finishes remaining work |
| Project completed | July 2027 | Phase wraps up |
From the start of the full closure to the reopening is roughly nine months, plus about one more month until the county lists the phase as complete.
The single-lane phase brings through traffic back past Coral Way and Sand Dollar Road, with crews still working beside it. Brevard County Public Works runs the job. The contractor is Johnson-Davis, Inc., and the contract is $2.38 million, paid with gas taxes and state appropriations through the Florida Department of Environmental Protection. The county's own pages set out how the work zone operates:
The second work zone matters for anyone who uses the full length of the riverfront road. Paradise Boulevard is where the detour sends drivers back onto Riverside. South of there, the county's Utility Services work means the road can still have cones and lane impacts after the drainage zone opens up.
This closure follows earlier work on the same road. In April, Space Coast Daily reported that the first phase, on Riverside Drive south of Sand Dollar Road and north of the entrance to The Sanctuary at Falcon Drive, was expected to be substantially complete at the end of that month. That phase replaced the old culvert crossing at the Sand Dollar Canal with dual 8-foot-by-3-foot concrete box culverts. The same report said crews would move on to retention walls along the canal east of the new culverts.
The current phase connects to those culverts. It upgrades the stormwater pipes under Riverside Drive so they drain into the new box culverts, with related drainage changes on Coral Way, Sand Pipe Road and Sand Dollar. The outlet at the canal was built first, and this phase extends the pipe network that feeds it toward Coral Way.
The Local Funding Initiative Request for Indialantic Stormwater Drainage Improvements Phase 2 explains why the county is digging here. It was filed with the Florida Senate in February 2025, with Senator Tom Wright as sponsor. It says the work is meant to relieve flooding in the Sandpipes neighborhood, the Palm Colony Club Condominium complex, along Atlantic Avenue and along Coral Way. The request estimates that about 5,000 people would be served.
The request describes Phase 2 as upgrades to the existing trunkline along Riverside Drive, with an extension toward Coral Way. It also covers relocating gravity and force main sewer lines that sit in the way. Those sewer conflicts are why the sidewalk near Coral Way will close now and then. The request priced the full Phase 2 package at $7,062,674 for fiscal year 2025–26. That total was 50% state money, 33% federal and 17% local.
The Senate funding request is direct about how much the project depends on outside money:
"The County is constrained by limited Municipal Services Taxing Unit (MSTU) collections and is only moving forward due to the availability of ARPA funds. The project will not move forward in lieu of the state funding."
The request also says the county expects to ask for more state funding in future years, about $3.5 million a year. So the pace of the next seven phases depends on more than the contractor's schedule. Each one needs its own funding before work can start.
Brevard County's proposed budget for fiscal year 2026–27 sets aside grant-match money for construction on Indialantic Stormwater Phase 4 and design on Phase 7, and it says the county aims to finish Phase 2 construction. The same proposed budget includes a separate Sand Dollar Canal project with a total of $2,046,503. It covers a denitrification bioreactor and sediment-removal system on county property near the Indian River Lagoon, designed to treat nutrient-heavy stormwater before it reaches the lagoon. Construction is scheduled for fiscal year 2026–27. That project is funded with $1.5 million in grants, $233,824 in sales tax revenue and $312,679 in assessments. The budget also lists $600,263 in utility support through September 2027 for "South Beaches: Indialantic Stormwater Improvements." That money covers sewer force main and gravity line bypasses and relocations as the drainage work needs them.
That puts a construction project named for the Sand Dollar Canal, at the north end of the current closure, on the county's proposed calendar for the same fiscal year as the single-lane phase. The county's August 10 release says additional phases "will be announced as details become available." The county project page is the main place for schedule updates. Brevard County Public Works Engineering takes questions at 321-637-5437, option 4. Public Works Engineer Wistenly Alphonse is listed as the project contact.
If you're planning to sell a home near Coral Way, Sand Pipe Road or Sand Dollar Road while this work is going on, I'm happy to walk you through how showings, buyer timing and the road schedule fit together this winter and spring. Reach out to Milly Akins to get your free home valuation, in English or Spanish.
Stay up to date on the latest real estate trends.
Milly is active in her community, loves spending time with her family and Belgian Malinois, and believes in helping others. She works with both buyers and sellers and is ready to show you what a seamless real estate experience feels like.